Independent and not affiliated with the FDA, MHRA, ISPE, PDA, or any agency. Get the appgoutham@madhadi.com
madhadi.comData Integrity & GxP Quality
Browse all topics -> Articles Templates & Procedures Learning paths GlossaryScenariosToolsRegulatory ReferencesLearning PathsTopics About Start here
Protocol Plug-and-play starting point Manufacturing Automation

Protocol: DCS/PLC Redundancy and Failover Qualification

A plug-and-play OQ protocol that proves a redundant controller pair, network path, or power supply actually fails over cleanly: forced-fault test cases, bumpless-transfer and alarm-state acceptance criteria, resynchronization checks, deviation handling, and a filled specimen.

Document type: Protocol

Read and copy the template below into your own quality system. It is a generic starting point for your own internal use, provided as is, with no warranty; see the Terms and License. Adopting it does not by itself create compliance.

This is a ready-to-use qualification protocol for a redundant automation system, a DCS controller pair, a redundant PLC configuration, a duplicated network path, or a dual power supply, that proves the failover behavior specified in the URS actually works. It is a companion to, not a replacement for, the general automation OQ protocol; run this one whenever the system under test claims high availability or redundancy as a design feature. Replace every <<FILL: ...>> placeholder, set your document numbers, and route it through document control. A worked filled specimen follows. This content is educational and general; adapt it to your own quality system and verify each reference against the current source.

Approval page

RoleNameSignatureDate
Author (automation / CSV)<<FILL>>
Reviewer (process SME)<<FILL>>
Reviewer (QA)<<FILL>>
Approver (Quality)<<FILL>>

Pre-approval is required before execution. Post-approval is required after execution and deviation closure.

FieldEntry
Protocol number<<FILL: OQ-ID>>
System name / ID<<FILL>>
Redundancy configuration under test<<FILL: e.g. hot-standby controller pair, dual redundant network, dual power feed>>
Version under test<<FILL: program/config version + checksum>>

1. Objective

To verify that <<FILL: SYSTEM NAME>> fails over from its primary to its secondary controller, network path, or power source without process upset, data loss, or loss of alarm state, within the vendor-specified or URS-specified failover time, and that the failed component can resynchronize and return to standby without manual data reconciliation.

2. Scope

This protocol covers every independent failure path the system claims to protect against: controller failure, network path failure, and, where applicable, power feed failure. It does not cover the discrete and analog functional testing already covered by the general automation OQ (<<FILL: reference>>); this protocol assumes that functional OQ has passed and tests only the failover behavior layered on top of it. It follows a passed and approved IQ (<<FILL: IQ reference>>).

3. System description

<<FILL: brief description: redundancy architecture (hot standby, warm standby, or load-shared), controller models and firmware, synchronization method, network topology for each redundant path, the specified failover time and bumpless-transfer behavior, controlled process and its criticality>>

4. Prerequisites

#PrerequisiteVerified (Y/N)By
1IQ and functional OQ complete, reviewed, approved
2Primary and secondary controllers confirmed synchronized before each test
3A documented, reversible method exists to force each fault (power disconnect, network disconnect, or vendor forced-failover command) without damaging equipment
4The process is in a state where a forced fault is safe to execute (test rig, non-product run, or a defined safe window)
5Monitoring in place to capture the process variable trend, alarm log, and event log through each test
6Executors trained on this protocol and on the safe fault-forcing method

5. Roles

RoleResponsibility
Executor (automation / CSV)Forces each fault, times the failover, records the trend and alarm evidence
Process SMEConfirms the process variable and alarm behavior through the transition are within the defined safe envelope
QAReviews execution, approves deviations, approves the protocol

6. Acceptance criteria (summary)

Test areaAcceptance criterion
Failover timeSecondary assumes control within the specified time from the forced fault
Bumpless transferNo step change in the process variable or controller output attributable to the switch
Alarm and event continuityNo active alarm is lost or silently cleared across the transition; the failover event itself is logged
HMI continuityOperator view of current process state and active alarms survives the switch without requiring reacknowledgment
Data continuityHistorian trend shows no gap in the data record across the transition
ResynchronizationThe failed unit rejoins as standby within the defined resync time with no manual data reconciliation
Independent pathsEach failure path (controller, network, power) tested independently; a shared single point of failure across paths is a finding, not a pass

7. Test cases

Record actual result, pass/fail, evidence reference, tester, and date for each.

TCFunctionStepExpected resultActualP/FEvidenceTester / date
RF-01Primary controller fault, steady stateWhile a critical loop is at steady state, disconnect power to the primary controllerSecondary assumes control within the specified time; no step change on the process variable trend; event logged
RF-02Primary controller fault, mid-transitionWhile a critical loop is actively ramping (for example a temperature ramp or a sequence step), disconnect power to the primarySecondary assumes control with no loss of the ramp or sequence state; no orphaned step
RF-03Alarm state through failoverWith an active, unacknowledged alarm present, force the primary faultThe alarm remains active and visible after the switch; it is not silently cleared or duplicated
RF-04Network path A failureDisconnect the first redundant network path onlyTraffic continues on path B with no historian data gap; a network-fault event is logged
RF-05Network path B failureDisconnect the second redundant network path only (independent test, not simultaneous with RF-04)Traffic continues on path A with no historian data gap; a network-fault event is logged
RF-06Power feed failure<<FILL: if dual power feeds exist>> disconnect one feedSystem continues on the remaining feed with no reset or data loss
RF-07ResynchronizationAfter RF-01 or RF-02, restore power to the failed controllerFailed unit resynchronizes and returns to standby within the defined time with no manual data reconciliation; a resync-complete event is logged
RF-08HMI continuityObserve the HMI through RF-01Operator view of current values and active alarms is continuous; no forced reacknowledgment or blank screen
RF-09<<FILL: system-specific redundancy function, e.g. load-shared controller rebalancing>><<FILL>><<FILL>>

8. Deviation handling

Any actual result that does not meet the expected result, including a failover that completes but bumps the process variable, loses an alarm, or exceeds the specified time, is recorded as a protocol deviation with a unique number, assessed for impact on the redundancy claim and on the system’s fitness for use, and resolved before the summary is approved. A failover that technically completes but outside the specified time or with a process bump is a deviation, not a pass with a note. Reference your deviation procedure <<FILL: SOP-ID>>.

9. Summary and conclusion

FieldEntry
Test cases executed<<FILL>>
Passed<<FILL>>
Deviations raised / closed<<FILL>>
Conclusion<<FILL: redundancy and failover behavior meets specification and the system may be relied on as high-availability / does not>>
RoleNameSignatureDate
Executor<<FILL>>
QA approval<<FILL>>

10. Attachments

  • Process variable trend export spanning each forced fault, start to resynchronization.
  • Alarm and event log export for each test case.
  • Timing evidence (timestamped video, data logger, or system event timestamps) supporting each measured failover time.
  • Network topology diagram showing the two paths tested independently.

References

21 CFR 211.68 (automatic, mechanical, and electronic equipment). 21 CFR Part 11 (electronic records and signatures). EU GMP Annex 11 (Computerised systems) and Annex 15 (Qualification and validation). ISPE GAMP 5, A Risk-Based Approach to Compliant GxP Computerized Systems (Second Edition, 2022).


Filled specimen

One executed test case, to show the level of evidence expected.

TCFunctionStepExpectedActualP/FEvidenceTester / date
RF-01Primary controller fault, steady stateBioreactor jacket temperature loop TIC-101 held at 37.0 C steady state; disconnected power to primary DCS controllerSecondary assumes control within 2 s per vendor spec; no step change on TIC-101.PV trend; failover event loggedSecondary active at 1.1 s; TIC-101.PV trend showed no discontinuity, held 36.9 to 37.1 C through the transition; event FAILOVER-0412 logged with timestampPassTrend export TR-RF01-20261123, event log EVT-0412M. Okafor, 23 Nov 2026

The acceptance language matters as much as the pass: the trend export is attached, the actual failover time is recorded against the specified time rather than a bare “passed,” and the alarm and event log confirm the transition was captured as a discrete, attributable event, not inferred from the absence of a complaint.

Common inspection findings this protocol prevents

  • A redundancy claim in the URS and FAT report that was never challenged with an actual forced fault in qualification.
  • A failover that completes but bumps the process variable or resets a sequence, treated as a pass because the secondary “took over” without checking what the process actually did.
  • Redundant controllers sharing a single non-redundant network switch or power feed, so the architecture is redundant on paper and a single point of failure in practice.
  • An active alarm silently lost or duplicated across a failover with no one noticing until an investigation needs the alarm history.
  • A failed unit that never demonstrably resynchronizes, so the system runs unprotected after the first fault until someone happens to check.

How to adapt this protocol

  1. Identify every independent failure path the redundancy design claims to protect (controller, network, power) and give each its own test case rather than one combined test.
  2. Set the specified failover and resync times from the vendor’s documented specification or your own URS, not from the first number that happened to pass.
  3. Schedule the forced-fault tests for a window where a real process bump is safe, a test rig, a non-product run, or a defined maintenance window, and document that justification.
  4. Capture the process variable trend and the alarm/event log as evidence for every test case, not just a pass/fail entry.
  5. Confirm every reference against the current published version before execution.
Use madhadi.com as an app Full screen, works offline, one tap from your home screen.