This is a ready-to-use plan for how a newly validated AI/ML model version actually enters production decision-making, the step between “the model passed validation” and “the model is now acting on live GxP decisions.” A validated model is approved on a held-out test set; how it is introduced to live traffic decides whether a problem that test set missed becomes a caught near-miss or a quality event. Replace every <<FILL: ...>> placeholder, set your document numbers, and route it through your normal review and approval. A filled specimen follows. This content is educational reference, not legal or regulatory advice.
1. Purpose and scope
This plan governs how <<FILL: MODEL NAME / VERSION>> moves from a validated, approved state into live production use, covering the deployment pattern chosen, the evidence collected before each promotion step, the criteria that permit advancing to the next step, and the rollback path if it does not. It applies to the initial production release of this model and to every subsequent version that reaches this system through the change control process <<FILL: reference>>. It does not cover the model validation itself (see <<FILL: validation protocol reference>>) or the ongoing monitoring once the model is fully live (see <<FILL: monitoring plan reference>>); this plan governs the transition between those two states.
2. Risk basis for the chosen approach
3. Deployment pattern selected
<<FILL: state the combination used, e.g. "shadow for 4 weeks, then a 10 percent canary widened in three steps over 6 weeks">>
- Promotion from one step to the next is a documented decision against the criteria in section 4, approved by
<<FILL: role, e.g. QA + System Owner>>. It is never an automatic action a metric triggers on its own, even where the pipeline is technically capable of auto-promotion.
- The model version that produced every shadow, canary, or challenger output is recorded with that output, so results at every step are attributable to a specific version and reviewable after the fact.
- A promotion decision that proceeds despite a borderline or failed criterion requires a documented rationale and an additional QA sign-off beyond the routine approval.
6. Rollback plan
The prior validated version is kept deployable and ready for an immediate switch back throughout the rollout; it is not decommissioned until the new version has completed full promotion and a defined stabilization period (<<FILL: e.g. 30 days>>) with no rollback event.
7. Roles
8. Acceptance criteria for this plan to be considered complete
- Every step in section 4 has documented entry criteria, exit criteria, and evidence actually collected against them.
- Every promotion decision is traceable to a named approver and a date.
- Every shadow, canary, or challenger output is attributable to the model version that produced it.
- The rollback path was available and ready to execute at every step, whether or not it was used.
- The prior validated version remained deployable until the defined stabilization period closed with no rollback event.
9. References
EU GMP Annex 11 (Computerised systems).
ISPE GAMP 5, A Risk-Based Approach to Compliant GxP Computerized Systems (Second Edition, 2022).
ICH Q9(R1), Quality Risk Management.
Filled specimen
A deviation-triage classifier moving from validation into production.
The specimen shows what the evidence trail looks like in practice: a measured number against the pre-set threshold at each step, a named approver, and a dated decision, not a single “deployment complete” entry with nothing behind it.
Common inspection findings this plan prevents
- A model promoted straight to 100 percent of traffic with no shadow or canary evidence that it behaves as specified on real production data.
- A promotion that happened automatically because a metric crossed a threshold, with no documented human release decision.
- Shadow or canary outputs that were never tagged with the model version that produced them, so the pre-promotion evidence cannot be reconstructed later.
- No rollback plan written down before the first promotion, so the response to a problem is improvised under pressure.
- The previous validated version decommissioned immediately on cutover, removing the rollback path before the new version has proven stable.
How to adapt this plan
- Choose the pattern, or combination of patterns, from the decision logic in the parent article’s rollout section, based on traffic volume, reversibility of the decision, and infrastructure compatibility.
- Set the exit criteria for each step from the model’s validated performance spec and release baseline, not from whatever number the first live sample happens to show.
- Size the canary slice and the widening schedule to the population: a low-volume population may need a longer shadow period instead of a meaningful slice.
- Reference your actual monitoring plan, change control procedure, and model validation report.
- Confirm every reference against the current published version before issue.